In Progress Road Works 09/11/23

This weeks in progress roadworks include –
Eaton Drive
Wilton Crescent
Lower Meadow Road
Green Villa Park
Manchester Road

Eaton Drive

Alderley Edge

side of 2 Meadow Brow to outside 15 (Footway, Carriageway)

Replace 293m of gas main with 18 associated connections and services.

Footway closure: Alternative route will be provided

16/10/2023 10:55

17/11/2023 00:00

CADENT GAS LIMITED: Cadent NW CMO

Wilton Crescent

Alderley Edge

The whole of Walton Crescent – Outside 1 to the side of 14 Eaton Drive (Footway, Carriageway)

Replace 527m of gas main with 50 associated connections and services.

Footway closure: Alternative route will be provided

17/10/2023 10:14

24/11/2023 00:00 CADENT GAS LIMITED: Cadent NW CMO

Lower Meadow Road

Handforth

LOWER MEADOW ROAD HANDFORTH WILMSLOW CHESHIRE EAST SK9 3LA LEADING TO COPPICE WAY NR RETAIL PARK (Carriageway)

TM REQUIRED TO PROVIDE SAFE WORKING ZONE FOR Safety for Engineer to work in Underground structure.

Footway closure: Alternative route will be provided

06/11/2023 10:12

17/11/2023 00:00

BT: OR DL

Green Villa Park

Wilmslow

12, SK9 6EJ (Footway, Carriageway)

IMMEDIATE WORKS open cut excavation is required to repair leaking main in footway/carraigeway

07/11/2023 17:16

13/11/2023 00:00

United Utilities Water Limited – C Water – Network

Manchester Road

Wilmslow

outside 137 in Carriageway (Carriageway)

Trace then excavate to repair gas escape and reinstate where possible

03/10/2023 10:00

17/11/2023 00:00

CADENT GAS LIMITED: Stockport Repair